Design Review Engineering of Shahpur Pumped Storage Project (5 x 300 MW + 2 x 150 MW), Baran District, Rajasthan |
| CLIENT: Greenko RJ01 IREP Private Limited |
| Year: 2024 – Ongoing |
| Project Features:
This is Standalone Pumped Storage Project having 10800 MW Storage Capacity and 1800 MW rating. The peak operation duration shall be 6.15 hrs. The major project components are:
|
| Scope:
Design Review Engineering of:
|
PSP
Sukhpura PSP
|
Preparation of Detailed Project Reports of Sukhpura Standalone Pumped Storage Project (2560 MW), Chittorgarh, Rajasthan |
| CLIENT: Greenko Group |
| Year: 2022 – Ongoing (Draft DPR under preparation) |
Scope:
|
Vijayanagar PSP
![]() |
|
Consultancy services for preparation of Detailed Project Report for 130 MW Vijayanagar pumped storage project in Vijayanagar, Karnataka, India |
| CLIENT: JSW Hydro Energy Limited |
| Year: 2021 – 2023 |
Scope:
|
Saundatti PSP
![]() |
|
Project Management Agency for Saundatti Pumped Storage Project (1600 MW), Karnataka, India |
| CLIENT: REC Limited |
| Year: 2024 – Ongoing |
| Project Features:
Saundatti PSP is located Belagavi district of Karnataka. It envisages creation of upper reservoir, water conducting systems, power house & lower reservoir near Karlakatti village. The scheme will involve construction of 4605 m long Geomembrane faced rockfill embankment dam for creation of upper reservoir of 0.735 TMC gross capacity. The Lower reservoir with 0.706 TMC gross capacity. The scheme envisages utilization of 193.35 m rated head and design discharge of 190.56 Cumecs for generation of 1280MW (4 units of 320 MW each) and 193.08 m rated head and design discharge of 95.81 Cumecs for generation of 320MW (2 units of 160 MW each). The major project components are:
|
Scope:
|
Gandikota PSP
|
Design Review Engineering for Gandikota Pumped Storage Project (1800 MW), Andhra Pradesh, India |
| CLIENT:
Adani Renewable Energy Fifty One Limited |
| Year:
2024 – Ongoing |
| Project Features:
This is Standalone Pumped Storage Project having IC 1800 MW. The peak operation duration shall be 6 hrs.The Gandikota Pumped Storage Project will comprise of two reservoirs. The existing Gandikota reservoir will be the lower reservoir and a new reservoir is to be constructed on the hilltop with low height dam of maximum height around 28.0m to create the desired storage capacity for energy storage and discharge. Lower dam is utilized for Irrigation, Drinking water and fisheries purpose. Evaporation losses if any will be recouped periodically from the existing Gandikota reservoir. |
| SCOPE:
Design Review Engineering of:
|
![]() |